Dimensions shall be measured nearest to a cm except for the thickness of slab which shall be measured correct to 0.5 cm. The areas shall be worked out nearest to 0.01 Sq. mt. The cubical contents shall be worked out to nearest 0.01 cubic metre.
Reinforced cement concrete whether cast-in-situ or pre cast shall be classified and measured separately as follows.
(a) Raft, footing, bases of columns and mass concrete etc. all work up to plinth level, column up to plinth level, plinth beams.
(b) Wall (any thickness) including attached pilasters, buttresses plinth and string course, fillets, column, pillars, piers, abutments, post and struts etc.
(c) Suspended floors, roofs, landings and balconies.
(d) Shelves
(e) Chajjas
(f) Lintel, beams and bressummers.
(g) Columns, pillars, piers, abutments, posts and struts.
(h) Stair-cases including waist or waist less slab but excluding landing except in (i) below.
(i) Spiral stair-case (including landing).
(j) Arches, arch ribs, domes and vaults.
(k) Chimneys and shafts.
(l) Well steining.
(m) Vertical and horizontal fins individually or forming box, louvers and facias.
(n) Kerbs, steps and the like.
(o) String courses, bands, coping, bed plates, anchor blocks, plain window sills and the like.
(p) Mouldings as in cornices, window sills etc.
(q) Shell, dome and folded plates.
(r) Extra for shuttering in circular work in plan.
Work under the following categories shall be measured separately.
(a) Rafts, footings, bases of columns etc. and mass concrete.
(b) All other items upto floor two level.
(c) From floor two level to floor three level and so on.
(d) R.C.C. above roof level shall be measured along with R.C.C. Work in floor just below.
(a) Ends of dis-similar materials (e.g. Joists, beams, post, girders, rafter, purlins, trusses, corbels steps etc.) upto 500 sq cm in cross-section.
(b) Opening upto 0.1. sqm.
(c) The volume occupied by reinforcement.
(d) The volume occupied by water pipes, conduits etc. not exceeding 25 sq cm each in cross sectional area. Nothing extra shall be paid for leaving and finishing such cavities and holes.
Measurement shall be taken before any rendering is done in concrete members. Measurement will not include rendering. The measurement of R.C.C. work between various units shall be regulated as below:
(a) Slabs shall be taken as running continuously through except when slab is monolithic with the beam. In that case it will be from the face to face of the beam.
b) Beams shall be measured from face to face of columns and shall be including haunches, if any, between columns and beam. The depth of the beam shall be from the bottom of slab to the bottom of beam if beam and slab are not monolithic. In case of monolithic construction where slabs are integrally connected with beam, the depth of beam shall be from the top of the slab to the bottom of beam.
(c) The columns measurements shall be taken through.
(d) Chajjas along with its bearing on wall shall be measured in cubic metre nearest to two places of decimal. When chajjas is combined with lintel, slab or beam, the projecting portion shall be measured as chajjas, built in bearing shall be measured as per item of lintel, slab or beam in which chajja bears.
(e) Where the band and lintels are of the same height and the band serves as lintel the portion of the band to be measured as lintel shall be for clear length of opening plus twice the over all depth of band.