CPWD Specifications, BRICK WORK

BRICK WORK

Measurements

  1. Brick work shall be measured in cubic metres unless otherwise specified. Any extra work over the specified dimensions shall be ignored. Dimensions shall be measured correct to the nearest 0.01 m i.e. 1 cm. Areas shall be calculated to the nearest 0.01 sq mtrs and the cubic contents shall be worked out to the nearest 0.01 cubic metres.
  2. Brick work shall be measured separately in the following stages:
    • (a) From foundation to floor one level (Plinth level)
    • (b) Plinth (floor one) level to floor two level
    • (c) Between two specified floor levels above floor two level
      • Note : (i) Brick work in parapet walls, mumty, lift machine room and water tanks constructed on the roof upto 1.2 m height above roof shall be measured together with the corresponding work of the floor next below.
  3. No deductions or additions shall be done and no extra payment made for the following :
    • (a) Ends of dissimilar materials (that is, joists, beams, lintels, posts, girders, rafters, purlins, trusses, corbels, steps, etc.); up to 0.1 m2 in section;
    • (b) Opening up to 0.1 m2 in area (see Note);
    • (c) Wall plates, bed plates, and bearing of slabs, chajjas and the like, where thickness does not exceed 10 cm and bearing does not extend over the full thickness of wall;
    • (d) Cement concrete blocks as for hold fasts and holding down bolts;
    • (e) Iron fixtures, such as wall ties, pipes upto 300 mm diameter and hold fasts for doors and windows; and
    • (f) Chases of section not exceeding 50 cm in girth.
    • (g) Bearing portion of drip course, bearing of moulding and cornice.
  4. Walls half brick thick and less shall each be measured separately in square metres stating thickness.
  5. Walls beyond half brick thickness shall be measured in multiples of half brick which shall be deemed to be inclusive of mortar joints.
  6. String courses, projecting pilasters, aprons, sills and other projections shall be fully described and measured separately in running metres stating dimensions of each projection.
  7. Square or rectangular pillars shall be measured separately in cubic metres in multiple of half brick.
  8. Circular pillars shall be measured separately in cubic metres as per actual dimensions.
  9. Brick work curved on plan shall be measured like the brick work in straight walls and shall include all cutting and wastage of bricks, tapered vertical joints and use of extra mortar, if any. Brick work curved on plan to a mean radius not exceeding six metres shall be measured separately and extra shall be payable over the rates for brick work in straight walls. Nothing extra shall be payable if the mean radius of the brick work curved in plan exceeds six metres.
  10. Tapered walls shall be measured net as walls and extra payment shall be allowed for making tapered surface for brick work in walls.
  11. Brick work with brick tiles shall be measured and paid for separately.

BRICK WORK IN ARCHES

Measurements

The length of the arch shall be measured as the mean of the extrados and intrados of the arch correct to a cm. The thickness of the arch shall be measured in multiples of the half brick. The breadth in the direction of the thickness of wall shall be measured as specified. The cubical contents shall be calculated in cubic metre, correct to two places of decimal. For arches exceeding 6 m in spans extra payment shall be made on the actual area of the soffit for additional cost of centring including all strutting, bolting, wedging, easing, striking and its removal.

HALF BRICK WORK

Measurements

The length and height of the wall shall be measured correct to a cm. The area shall be calculated in sq.m. where half brick wall is joined to the main walls of one brick or greater thickness and measurements for half brick wall shall be taken for its clear length from the face of the thicker wall.

HONEY COMB BRICK WORK

Measurements

The length and height shall be measured correct to a cm. Area shall be calculated in square metres correct to two places of decimal. Honeycomb openings shall not be deducted.

JOINING OLD BRICK WORK WITH NEW BRICK WORK

Measurements

The height and thickness of vertical face in contact with new work shall be measured to the nearest 0.01 m and the area shall be calculated to the nearest 0.01 sqm.

BRICK EDGING

Measurements

The brick edging shall be measured in running metre correct a cm.